Besseling Mechanical was the Prime Contractor for this project. The project involved the demolition of two existing cooling towers and the installation of two new 5,000 USGPM cooling towers, existing condenser water pumps were also replaced. In addition, approximately 1,600 feet of 24” condenser water piping was installed underground from the hospital’s mechanical room to the cooling towers located on top of an ancillary building.